Report about all the works and the achieved ones

1- water crosses

Branch

Aimed

No started

Being working

Expected

finished

Ras Ejdeer

8

0

0

0

8

Alzawia

37

3

0

1

33

Tagora – Algarabolli

21

21

0

0

0

Alkoms

56

22

11

13

19

Zeleten

18

0

0

1

17

Musrata

87

15

11

1

60

Sert

34

16

10

0

8

Tobroq

15

0

3

1

11


2- electric crossers



Branch

Aimed

No started

Being working

Expected

finished

Ras Ejdeer

85

8

0

7

70

Alzawia

121

26

2

0

93

Tagora – Algarabolli

75

15

10

0

50

Alkoms

73

29

5

0

39

Zeleten

54

2

0

0

52

Musrata

78

32

18

0

28

Sert

29

7

0

2

20

Tobroq

6

0

0

0

6


3- underground crossers



Branch

Aimed

No started

Being working

Expected

finished

Ras Ejdeer

2

1

0

1

-

Alzawia

-

-

-

-

-

Tagora – Algarabolli

5

-

3

1

1

Alkoms

6

5

1

-

-

Zeleten

-

-

-

-

-

Musrata

-

-

-

-

-

Sert

-

-

-

-

-

Tobroq

-

-

-

-

-


4- Earth works



Branch

Aimed

Achieved

Ras Ejdeer

115393500 m3

515284665 m3

Alzawia

102099700 m3

60926314  m3

Tagora – Algarabolli

320298800 m3

114434500 m3

Alkoms

437296700 m3

210638300 m3

Zeleten

57518300 m3

32000000 m3

Musrata

151560700 m3

81580000 m3

Sert

31896000 m3

13303965 m3

Tobroq

35432600 m3

14502900 m3



Branch

Percent of aimed works for the branch to aimed  works for all the project 

Percent of achieved works to the aimed for the branch

Ras Ejdeer

9.22%

44.6%

Alzawia

8.16%

59.7%

Tagora – Algarabolli

25.59%

45.1%

Alkoms

34.94%

48.2%

Zeleten

4.49%

56.1%

Musrata

12.11%

53.8%

Sert

2.55%

41.7%

Tobroq

2.83%

40.9%

<<Back ..... Next>>

 




About Libya Libya News [ Archive ] Libya Events Libya Tenders Libya Laws Libya Regulation

about us | Contact us | Join us | Home page

Copyright © 1999 - 2007 Libyaninvestment.com
All Rights Reserved.

Mohamed A.M.Sulaiman