- The main components of the project
Item |
Description |
| Network length |
3170 km |
| Stations |
96 |
| Bridges |
554 |
| Crossers |
1205 |
| Earth works |
115 million m3 |
| Concrete works |
2 500 000 m3 |
| Steel for concrete |
261 000 tons |
| Steelbars |
370 000 tons |
| Concrete Rafters |
6 800 000 |
| Fastenings |
27 200 000 pcs |
| Rock fragments |
11 600 000 m3 |
| Flint concrete |
2 500 000 m3 |
| Cement |
800 000 tons |
| Locomotives |
244 units |
| Coaches |
8 642 |
| Job opportunities |
10 000 |
Item |
Description |
| Designed speed |
160 km/h |
| Operating speed |
120 - 140 km/h for passengers trains 80 – 100 km/h cargo trains |
| Axial load for line |
22 ton |
| Width |
1435 mm |
| Line type |
Single |
| Maximum gradient |
0.6 % |
| Minimum horizontal radius |
1600 m |
| Minimum vertical curvature |
10 000 m |
| Track width |
7.20 m |
| Bars type |
54-60 kg/m |
| Switches & turnouts |
UIC |
| Fastening system |
Elastic |
<<Back ...... Next>>
|
|