| No. |
Name of The Project |
Project Location |
Main components |
Project target |
Executive status |
E. O. date |
Contracted party |
Contracted value |
| 1 |
Musrata Dual cycle power plant |
Musrata (Iron and steel complex) |
Project is formed from two gas generation units and one steam generation unit with a capacity of 750 Mega Watt with full annexes |
The project aims development of capabilities for electric energy production to participate in the increased demand for electric energy |
Project was contracted and we are awaiting for opening L/C |
The gas powered plant in 9/2009 |
Daewoo Engineering & Construction Co.Ltd |
593,893,306 LD |
| 2 |
Benghazi dual cycle power plant project |
Benghazi (North Benghazi's plant) |
Project is formed from two gas generation units and one steam generation unit with a capacity of 750 Mega Watt with full annexes |
The project aims development of capabilities for electric energy production to participate in the increased demand for electric energy |
Project was contracted and we are awaiting for opening L/C |
The gas-powered
plant in 9/2009 |
Daewoo Engineering & Construction Co.Ltd |
516,547,884 LD |
| 3 |
Gulf's steam-powered plant |
Sirte |
The project is formed from four steam generation units with a capacity 1,400 Mega Watt with full annexes |
The project aims development of capabilities for electric energy production to participate in the increased demand for electric energy |
Permission for contracting is issued and project is under contracting arrangements |
As from beginning: 12/2010 |
The Electric Power Development Co.
(EPCM) |
1,794,573,414 LD |